A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into 12 equal monthly allocations. At the end of the fourth month of that fiscal year, the total amount actually spent on the project was $4,580. By how much was the project over its budget?
  • A$ 380
  • B$ 540
  • C$1,050
  • D$1,380
  • E$1,430
显示答案
正确答案: A