A construction company was paid a total of $500,000 for a construction project. The company`s only costs for the project were for labor and materials. Was the company`s profit for the project greater than $150,000?
(1)The company`s total cost was three times its cost for materials.
(2)The company`s profit was greater than its cost for labor.